10 FE practice problems: comparing alternatives, with solutions
These ten original problems practice comparing alternatives, a topic from the FE exam specification, using the Engineering Economics, Benefit-Cost Analysis part of the FE Reference Handbook 10.6. Each problem gives the situation and the values with units. Work it with the handbook PDF open and commit to an answer before you open the solution. Every solution shows the handbook page, the equation, the substitution with units, a size check, and the mistake behind each wrong option, so a wrong pick tells you exactly what to fix.
How to use these problems
Give each problem an honest attempt before you open the solution: write the given values with units, find the equation in the FE Reference Handbook PDF, and commit to an answer. Then compare line by line. If you picked a wrong option, read the note for that option; each one names the mistake that produces it.
The problems
Problem 1 · FE, Comparing alternatives
A county flood-control project costs $690,000 now and $26,000 per year to operate. It prevents damages worth $138,000 per year for 23 years. At a MARR of 6% per year, the conventional benefit-cost ratio is most nearly:
Handbook: Engineering Economics, Benefit-Cost Analysis, FE Reference Handbook 10.6
Show the worked solution
- Answer
- B (1.68)
- Given
- P = $690,000, C = $26,000, B = $138,000, n = 23 years, i = 6% per year
- Find
- conventional benefit-cost ratio
- Handbook
- Engineering Economics, Benefit-Cost Analysis and factor formulas, pages 237 and 240
- Equation
B/C = PW(benefits)/PW(costs), with (P/A, i, n) = [(1 + i)ⁿ - 1]/[i(1 + i)ⁿ]- Substitute
(P/A, 6%, 23) = 12.3034 (factor table, i = 6%)PW of benefits = $138,000 × 12.3034 = $1,698,000PW of costs = $690,000 + $26,000 × 12.3034 = $1,010,000B/C = $1,698,000/$1,010,000 = 1.68
- Result
- 1.68, 3 significant figures
- Check
- B/C ≥ 1, so the project is justified at 6%.
- Why the others are wrong
- A: is the modified ratio (benefits minus O&M over first cost), not the conventional one asked for
- C: left the yearly operating cost out of the cost side
- D: is the cost-to-benefit ratio (inverted)
Problem 2 · FE, Comparing alternatives
A treatment plant buys a centrifuge for $60,000. It has a 14-year life and a salvage value of $2,000. Using straight-line depreciation, the book value at the end of year 4 is most nearly:
Handbook: Engineering Economics, Depreciation and Book Value, FE Reference Handbook 10.6
Show the worked solution
- Answer
- C ($43,400)
- Given
- P = $60,000, S = $2,000, n = 14 years, k = 4 years
- Find
- book value after year 4 ($)
- Handbook
- Engineering Economics, Depreciation (Straight Line) and Book Value, page 236
- Equation
Dj = (P - S)/n; BV = P - Σ Dj- Substitute
Dj = (P - S)/n = ($60,000 - $2,000)/14 = $4,143 per yearBV after 4 years = P - 4 × Dj = $60,000 - 4 × $4,143 = $43,400
- Result
- $43,400, 3 significant figures
- Check
- the book value falls in equal steps from $60,000 to the salvage value $2,000 at year 14.
- Why the others are wrong
- A: is the accumulated depreciation, not the book value
- B: is the yearly depreciation charge, not the book value
- D: is the book value after 5 years
Problem 3 · FE, Comparing alternatives
A treatment plant buys a centrifuge for $92,000. It has a 6-year life and a salvage value of $10,000. Using straight-line depreciation, the book value at the end of year 5 is most nearly:
Handbook: Engineering Economics, Depreciation and Book Value, FE Reference Handbook 10.6
Show the worked solution
- Answer
- C ($23,700)
- Given
- P = $92,000, S = $10,000, n = 6 years, k = 5 years
- Find
- book value after year 5 ($)
- Handbook
- Engineering Economics, Depreciation (Straight Line) and Book Value, page 236
- Equation
Dj = (P - S)/n; BV = P - Σ Dj- Substitute
Dj = (P - S)/n = ($92,000 - $10,000)/6 = $13,670 per yearBV after 5 years = P - 5 × Dj = $92,000 - 5 × $13,670 = $23,700
- Result
- $23,700, 3 significant figures
- Check
- the book value falls in equal steps from $92,000 to the salvage value $10,000 at year 6.
- Why the others are wrong
- A: is the book value after 6 years
- B: subtracted only one year of depreciation
- D: is the yearly depreciation charge, not the book value
Problem 4 · FE, Comparing alternatives
A treatment plant buys a centrifuge for $62,000. It has a 11-year life and a salvage value of $6,000. Using straight-line depreciation, the book value at the end of year 9 is most nearly:
Handbook: Engineering Economics, Depreciation and Book Value, FE Reference Handbook 10.6
Show the worked solution
- Answer
- C ($16,200)
- Given
- P = $62,000, S = $6,000, n = 11 years, k = 9 years
- Find
- book value after year 9 ($)
- Handbook
- Engineering Economics, Depreciation (Straight Line) and Book Value, page 236
- Equation
Dj = (P - S)/n; BV = P - Σ Dj- Substitute
Dj = (P - S)/n = ($62,000 - $6,000)/11 = $5,091 per yearBV after 9 years = P - 9 × Dj = $62,000 - 9 × $5,091 = $16,200
- Result
- $16,200, 3 significant figures
- Check
- the book value falls in equal steps from $62,000 to the salvage value $6,000 at year 11.
- Why the others are wrong
- A: is the accumulated depreciation, not the book value
- B: subtracted only one year of depreciation
- D: is the yearly depreciation charge, not the book value
Problem 5 · FE, Comparing alternatives
A precast plant has fixed costs of $311,000 per year. Each manhole section sells for $144 and costs $11 to make. The breakeven production is most nearly:
Handbook: Engineering Economics, Breakeven Analysis, FE Reference Handbook 10.6
Show the worked solution
- Answer
- C (2,340 units/yr)
- Given
- F = $311,000, price = $144, v = $11
- Find
- breakeven quantity (units per year)
- Handbook
- Engineering Economics, Breakeven Analysis, page 236
- Equation
Q = F/(price - variable cost per unit)- Substitute
At breakeven, revenue = cost: price·Q = F + v·QQ = F/(price - v) = $311,000/($144 - $11) = 2,340 units per year
- Result
- 2,340 units/yr, 3 significant figures
- Check
- at Q = 2,340, revenue $337,000 equals cost $337,000.
- Why the others are wrong
- A: divided the fixed cost by the price, ignoring the variable cost
- B: added the variable cost to the price
- D: divided the fixed cost by the variable cost
Problem 6 · FE, Comparing alternatives
A county flood-control project costs $670,000 now and $4,500 per year to operate. It prevents damages worth $36,000 per year for 21 years. At a MARR of 6% per year, the conventional benefit-cost ratio is most nearly:
Handbook: Engineering Economics, Benefit-Cost Analysis, FE Reference Handbook 10.6
Show the worked solution
- Answer
- D (0.586)
- Given
- P = $670,000, C = $4,500, B = $36,000, n = 21 years, i = 6% per year
- Find
- conventional benefit-cost ratio
- Handbook
- Engineering Economics, Benefit-Cost Analysis and factor formulas, pages 237 and 240
- Equation
B/C = PW(benefits)/PW(costs), with (P/A, i, n) = [(1 + i)ⁿ - 1]/[i(1 + i)ⁿ]- Substitute
(P/A, 6%, 21) = 11.7641 (factor table, i = 6%)PW of benefits = $36,000 × 11.7641 = $423,500PW of costs = $670,000 + $4,500 × 11.7641 = $722,900B/C = $423,500/$722,900 = 0.586
- Result
- 0.586, 3 significant figures
- Check
- B/C < 1, so the project is not justified at 6%.
- Why the others are wrong
- A: divided one year of benefit by the first cost plus one year of cost
- B: used undiscounted totals
- C: is the cost-to-benefit ratio (inverted)
Problem 7 · FE, Comparing alternatives
A precast plant has fixed costs of $559,000 per year. Each manhole section sells for $138 and costs $91 to make. The breakeven production is most nearly:
Handbook: Engineering Economics, Breakeven Analysis, FE Reference Handbook 10.6
Show the worked solution
- Answer
- A (11,900 units/yr)
- Given
- F = $559,000, price = $138, v = $91
- Find
- breakeven quantity (units per year)
- Handbook
- Engineering Economics, Breakeven Analysis, page 236
- Equation
Q = F/(price - variable cost per unit)- Substitute
At breakeven, revenue = cost: price·Q = F + v·QQ = F/(price - v) = $559,000/($138 - $91) = 11,900 units per year
- Result
- 11,900 units/yr, 3 significant figures
- Check
- at Q = 11,900, revenue $1,640,000 equals cost $1,640,000.
- Why the others are wrong
- B: added one unit's variable cost to the fixed cost
- C: divided the fixed cost by the variable cost
- D: added the variable cost to the price
Problem 8 · FE, Comparing alternatives
A precast plant has fixed costs of $906,000 per year. Each manhole section sells for $96 and costs $54 to make. The breakeven production is most nearly:
Handbook: Engineering Economics, Breakeven Analysis, FE Reference Handbook 10.6
Show the worked solution
- Answer
- C (21,600 units/yr)
- Given
- F = $906,000, price = $96, v = $54
- Find
- breakeven quantity (units per year)
- Handbook
- Engineering Economics, Breakeven Analysis, page 236
- Equation
Q = F/(price - variable cost per unit)- Substitute
At breakeven, revenue = cost: price·Q = F + v·QQ = F/(price - v) = $906,000/($96 - $54) = 21,600 units per year
- Result
- 21,600 units/yr, 3 significant figures
- Check
- at Q = 21,600, revenue $2,070,000 equals cost $2,070,000.
- Why the others are wrong
- A: divided the fixed cost by the variable cost
- B: added the variable cost to the price
- D: divided the fixed cost by the price, ignoring the variable cost
Problem 9 · FE, Comparing alternatives
A county flood-control project costs $490,000 now and $7,000 per year to operate. It prevents damages worth $64,000 per year for 13 years. At a MARR of 4% per year, the conventional benefit-cost ratio is most nearly:
Handbook: Engineering Economics, Benefit-Cost Analysis, FE Reference Handbook 10.6
Show the worked solution
- Answer
- B (1.14)
- Given
- P = $490,000, C = $7,000, B = $64,000, n = 13 years, i = 4% per year
- Find
- conventional benefit-cost ratio
- Handbook
- Engineering Economics, Benefit-Cost Analysis and factor formulas, pages 237 and 240
- Equation
B/C = PW(benefits)/PW(costs), with (P/A, i, n) = [(1 + i)ⁿ - 1]/[i(1 + i)ⁿ]- Substitute
(P/A, 4%, 13) = 9.9856 (factor table, i = 4%)PW of benefits = $64,000 × 9.9856 = $639,100PW of costs = $490,000 + $7,000 × 9.9856 = $559,900B/C = $639,100/$559,900 = 1.14
- Result
- 1.14, 3 significant figures
- Check
- B/C ≥ 1, so the project is justified at 4%.
- Why the others are wrong
- A: divided one year of benefit by the first cost plus one year of cost
- C: left the yearly operating cost out of the cost side
- D: used undiscounted totals
Problem 10 · FE, Comparing alternatives
A precast plant has fixed costs of $508,000 per year. Each manhole section sells for $119 and costs $58 to make. The breakeven production is most nearly:
Handbook: Engineering Economics, Breakeven Analysis, FE Reference Handbook 10.6
Show the worked solution
- Answer
- B (8,330 units/yr)
- Given
- F = $508,000, price = $119, v = $58
- Find
- breakeven quantity (units per year)
- Handbook
- Engineering Economics, Breakeven Analysis, page 236
- Equation
Q = F/(price - variable cost per unit)- Substitute
At breakeven, revenue = cost: price·Q = F + v·QQ = F/(price - v) = $508,000/($119 - $58) = 8,330 units per year
- Result
- 8,330 units/yr, 3 significant figures
- Check
- at Q = 8,330, revenue $991,000 equals cost $991,000.
- Why the others are wrong
- A: divided the fixed cost by the variable cost
- C: divided the fixed cost by the price, ignoring the variable cost
- D: added the variable cost to the price
A new problem posts every day inside the lab, with the full worked solution the same evening.
Frequently asked questions
Where is comparing alternatives in the FE Reference Handbook?
Look in the Engineering Economics, Benefit-Cost Analysis part of FE Reference Handbook 10.6. Each solution gives the exact page, so you can practice finding it in the PDF the way you will on exam day.
Are these real FE exam questions?
No. They are original problems generated from the handbook formulas and checked by code. Real exam questions are confidential, and sharing them breaks the NCEES agreement every examinee accepts.
How do I check my answer before opening the solution?
Check the units of your result and whether its size makes sense for the situation. Each solution ends with the same kind of check, so you can compare your habit with ours.
Sources
- NCEES FE Civil CBT exam specifications (PDF). Retrieved October 3, 2026.
- NCEES FE Environmental CBT exam specifications (PDF). Retrieved October 3, 2026.
- NCEES FE Mechanical CBT exam specifications (PDF). Retrieved October 3, 2026.
- NCEES FE Reference Handbook 10.6 (free PDF in MyNCEES). Retrieved October 3, 2026.